Client                    Rio Tinto

Main Contractor   ABB

Client

Rio Tinto

Main Contractor

ABB

Contributing to the increase in iron ore mining at Parker Point for Rio Tinto.

Scope of work

  • Laying feeder cables on above ground cable trays
  • 4 way pilot cables providing over 4000 metres of cabling
  • Safe delivery of confined space work where cables are routed underground
  • Improvements and modifications to equipment including
    • Buzzbars
    • Insulators
    • HV Jointing
    • Upgrading transformers in zone substations with 22kV to 33kV